Late 2016 Activities

Exhibitions and site preparation

During the months of September and October, the stakeholder team and other staff

from the project team delivered 11 Public Information Exhibitions spread along the

route of the scheme and we welcomed a total of 2845 visitors.

These exhibitions supplied scheme wide information in relation to many subjects and

members of the project team with a cross section of specialist knowledge were

available at each location to answer questions.

The exhibition panels and plans on display are now on the A14 website.

Since September the A14 project team have been undertaking preparatory works in

advance of main construction.

These works have included site clearance, ecology mitigation (for badgers, water

vole, great crested newts and bats), boundary fencing and archaeology.

We have also been constructing our site compounds at Alconbury, Brampton,

Ermine Street and Swavesey.

Section 1 & 2 -

Alconbury to the East Coast Main Line

On the A1 we are installing a new safety barrier along the highway verge. This will

allow our staff to safely work behind and will also ensure we keep traffic moving at

normal speeds with full lane widths for as long as possible.

One of the original ‘Great North Road’ milestones has been removed from the A1

verge and has been surveyed and recorded. We are talking to Alconbury Parish

Council about storage and relocation in the future.

Recent resurfacing work carried out north of Buckden is not part of the A14

improvement scheme but is part of an ongoing maintenance programme. We are

talking to the Highways England contractor undertaking the work to understand and

help manage concerns that the local community has raised.

Section 3 -

East Coast Main Line to Swavesey

On Ermine Street, following comments from the public, the traffic management and

signage has been adjusted and the compound access points upgraded to improve

the traffic flow and safety. We are continuing to monitor the situation.

Section 4 & 5 -

Swavesey to Milton

Work continued on the construction of the main project compound at Swavesey

Junction. Archaeology and site clearance are taking place alongside the A14

between Swavesey and Girton.